Proběhla generální modernizace ohřívací pece pro VÍTKOVICE HEAVY MACHINERY a.s. NS340 – Kunčice. Pec je osazena plochoplamennými hořáky.
Řízený ohřev výkovků
Řídicí systém umožňuje přesné řízení tepelného režimu...
|
|
During the modernization of the car-type furnace No. 2 was almost the whole furnace pull down – only steel pillars of the side walls were used. The whole project was managed by Vítkovice Strojírenství (Engineering) a.s., our company supplied...
|
|
The original car-type furnace No. 1 was completely pulled down, including steel frame and regeneration equipment for the preheating of the input air. The project was managed by the VITKOVICE MECHANIKA Co., our company was sub supplier of the...
|
|
4. Overhauling and modernization of the pusher furnace No. 2 for EVRAZ VÍTKOVICE STEEL, Co., Ostrava
Modernization of the heating system of the pusher furnace No. 2 was based on the new system for burning of natural gas as well as gas produced by oxygen converter. The mixing station and burners were modification by our designer to be able to burn...
|
|
As a part of the modernization project of pusher furnace in the rolling – mill JTII we made a replace of the control system with new Allen - Bradley SLC 500 system. New automation control system is connected to the operator´s station and...
|
|
The overhauling and modernization project included technical conception of the rebuilding of the furnace, technical specifications and drawings, repair and assembly of the steel construction part, supply and assembly of the new heating system...
|
|
In 2008 was executed the project of overhauling and modernization of the pre-heating furnace No. 4 in NS 340 Dpt. In VÍTKOVICE HEAVY MACHINERY Co. We were a sub supplier of the new heating system using burners from BLOOM Engineering Co. with...
|
|
In 2008 the project of overhauling and modernization of pre-heating furnace No. 3 in NS 340 in VITKOVICE HEAVY MACHINERY was completed. Our company supplied a complex rebuilding of the heating system with hot air burner from BLOOMENGINEERING Co....
|
|
We replaced the entire heating system and input pipeline due to conversion to the using of natural gas. Heating system consists of high speed burners supplied by Bloom Engineering. The refractory lining was partly renewed and steel frame...
|
|
The project of modernization of control system had a task to replace obsolete relays control system for computer based control system. During the heating of the material for the mill line is the waste heat energy is used for preheating of the...
|